GM Tower, Burwood

Demolition of existing buildings & construction of 25 storey mixed use development building comprising of 131 x residential units, 10,478m2 of commercial floor space and 3,573m2 of retail space over a 4 level basement.                                                                                                                                                                          (Area / yield summary) – approx. 3,943 m2 site
• Total end value – construction costs $68m
• Timeline – Commenced August 2014, completed May 2016 Sept 2016 (25 months)
• Design team – Urban Link (arch), ABC Consultants (struc), TDL (hyd), CBS Engineers (elec), Vision Dynamics (L/scape), ING Consultant (s/water), Traffic Solutions (traffic), CBS (PCA), SDG (survey), JK Geotechnics (geo tech), Shelmerdines (Level 1 ASP), Rodney Stevens (acoustic), Exova (Fire Engineer)
• Developer / Head contractor – Urban Apartments